City Improvement Projects

 

Click here to view a map of all 2017 street improvement projects within the City of Ramsey.

 

  • Riverdale Drive Extension - Traprock St. to Ramsey Blvd. (IP #16-20)
    • Riverdale Drive will be extended between Traprock Street and Ramsey Boulevard
    • This project will complete the south Highway 10 frontage road between Llama Street and Tungsten Street
    • Construction will begin September 5
    • Construction will be substantially complete by November 2017
    • Final completion will occur in 2018
  • Sunwood Drive Reconstruction (IP #17-00)
    • The bituminous pavement on Sunwood Drive between Ramsey Boulevard and Bunker Lake Boulevard is being reconstructed using a stabilized full-depth reclamation (SFDR) process
    • Construction began June 30
    • Construction will be substantially complete by September 1
    • Final completion will occur in 2018
  • Alpine Drive Reconstruction (IP #17-01)
    • The bituminous pavement on Alpine Drive between Armstrong Boulevard and Variolite Street is being reconstructed using a full-depth reclamation (FDR) process
    • Construction began July 25
    • Construction will be substantially complete by September 1
    • Final completion will occur in 2018
    • Alpine Drive will remain closed to traffic through August 2017
  • 2017 Crackseal and Sealcoat Improvements (IP #17-03)
    • Approximately 13.6 miles of public streets throughout the City will be crack sealed and sealcoated
    • Construction will occur in late August
    • Construction will be substantially complete by September 1
    • Streets will be swept several times to remove loose rock
  • Sunwood Drive Striping Improvements (IP #17-04)
    • The concrete pavement on Sunwood Drive between Zeolite Street and Rhinestone will be restriped
    • The existing center two-way turn lane is being replaced with dedicated left turn lanes
    • Several dedicated right turn lanes are being added
    • Construction will occur in late August
    • Construction will be complete by September 1
  • Bunker Lake Boulevard Utilities Extensions (IP #17-09)
    • Trunk Sanitary Sewer and Watermain are being extended along Bunker Lake Boulevard to Puma Street 
    • Construction began August 14
    • Construction will be complete by September 1
    • Work will include single lane closures during working hours