2021 Neighborhood Pavement Overlay Improvements IP 21-04

Update January 27, 2021

On January 12, 2021, the Ramsey City Council ordered plans and specifications for City Improvement Project #21-04, 2021 Neighborhood Pavement Overlay Improvements, which proposes to overlay 1.81 miles of bituminous pavement on numerous neighborhood street segments within the following developments. Property owners will not be assessed for any of the costs for these improvements.

  • Birch Hill Lodges
  • Ferrum 1st & 2nd
  • Gateway Industrial Park
  • Mallard Ponds
  • Northfork Itasca Point
  • Northfork St. Andrews
  • Oakridge Industrial Park
  • Rabbit Run
  • Ramsey Meadows 2nd

Overlaying these street segments in 2021, which is identified in the 2021 – 2030 Capital Improvement Program, will allow the City to maintain these streets in the most cost-effective manner throughout the serviceable life of the streets.


Tentative Project Schedule

March 9 - Approve Plans and Specifications / Authorize Ads for Bids

March 12, and March 19 - Publish Ads for Bids

April 6 - Bid Opening

April 13 - Accepts Bids /Award Contract

Early June - Begin Construction

Mid August - Contractor Completes Construction


Click here to view the street segments proposed to receive bituminous pavement overlay improvements in 2021.

 

Estimated project costs are based on anticipated 2021 construction costs and total $690,000. Funding is proposed to come from the Pavement Management Fund ($643,000) and the Stormwater Utility Fund ($47,000). Property owners will not be assessed for any of the costs for these improvements.


The City Council has not yet approved the final project.